How to Pour the Transformer of a Medium Frequency Spot Welding Machine?

The transformer is a crucial component of a medium frequency spot welding machine, as it transforms the input voltage into the desired welding current. Proper pouring of the transformer is essential to ensure its efficient operation and longevity. In this article, we will discuss how to pour the transformer of a medium frequency spot welding machine.
IF spot welder
Step 1: Prepare the Molds
The molds for pouring the transformer should be made of heat-resistant materials, such as cast iron or steel. The molds should be cleaned and coated with a mold release agent to prevent the transformer from sticking to the molds. The molds should also be assembled tightly to prevent any leaks.
Step 2: Prepare the Core
The transformer core should be cleaned and inspected for any defects before pouring. Any defects should be repaired before proceeding with the pouring process.
Step 3: Mix the Insulation Material
The insulation material for the transformer should be mixed according to the manufacturer’s instructions. The insulation material should be free of any lumps and should have a consistent texture.
Step 4: Pour the Insulation Material
The insulation material should be poured into the molds in layers. Each layer should be compacted using a vibratory table or a hammer to ensure that there are no voids in the insulation material. The insulation material should be allowed to cure for the recommended amount of time before proceeding to the next step.
Step 5: Pour the Copper Windings
The copper windings should be poured into the molds after the insulation material has cured. The copper windings should be arranged according to the design of the transformer. The copper windings should be compacted using a vibratory table or a hammer to ensure that there are no voids in the windings.
Step 6: Pour the Final Layer of Insulation Material
The final layer of insulation material should be poured over the copper windings. The insulation material should be compacted using a vibratory table or a hammer to ensure that there are no voids in the insulation material. The insulation material should be allowed to cure for the recommended amount of time before proceeding to the next step.
Step 7: Finish the Transformer
After the insulation material has cured, the molds should be removed, and the transformer should be cleaned and inspected for any defects. Any defects should be repaired before the transformer is installed in the welding machine.
In conclusion, pouring the transformer of a medium frequency spot welding machine requires careful attention to detail and adherence to manufacturer’s instructions. By following these steps, the transformer can be poured efficiently and effectively, ensuring the proper operation of the welding machine.